Zurich Reception

Zurich

Building N1 & N2, Aerospace Park

On the back of the successful delivery of Building 3000C, Solent Business Park, Fareham for Zurich Financial Services, BW Interiors were invited to negotiate for this prestigious project subsequent to a successful preconstruction period where BW Interiors worked with the professional team to achieve design and contract sum 'sign-off' within a 6 week period, works commenced on site.

Buildings N1 and N2 are office buildings on adjacent plots comprising approximately 47,000 sq ft and 65,000 sq ft respectively. Both buildings were constructed to a similar specification and comprise ground and 2No upper floors.

The works comprised the stripping out of the existing office areas and the fitting out of the buildings for occupation by Zurich. The works included creation of open plan office space together with cellular office and meeting room space and ancillary areas including main comms and IT hub rooms and resources, filing, breakout, vending, reception, and kiosk / café areas.

Lift works were limited to those required for DDA compliance. Lighting and small power to office areas were renewed as part of the works and ductwork, pipework, fan coil units and grilles, retained and refurbished / modified / supplemented wherever possible to achieve the most economic solution for the employer.

The works were completed in sections to allow progressive occupation by Zurich.

 

Project Details
 Client  Zurich
 Project Manager  Savills
 Architect  SPPARC
Form of Contract  JCT 1998 D&B
 Value  £6,000,000
 Size  112,000 sq ft
 Programme Period  21 weeks