Transworld

TransWorld International

Burlington Lane, London W4

This was an unusual fast track fit-out project of this three-storey building for the broadcasting company, Network of the World, subsidiary of TransWorld International.

Completed within very demanding timescales to keep to the roll-out and infrastructure requirements for the business of Network of the World, the project involved high quality cellular and open planned office space as well as boardroom, meeting rooms, fully operational kitchens and reception area. As the company run a 24/7 live broadcast the installation of UPS and generator standby supplies was critical.

The greatest challenge was creating a twenty-first century, futuristic style to the 1970s constructed building to reflect the multi-media business nature of the client.

Project Details
Client TransWorld International
Project Manager John Melville Partnership
Architect Turner Legg Consulting
Form of Contract Management Contract
Value £5,197,818
Size 45,000 sq ft
Programme Period 16 weeks

Back to Media

*