Mediaedge - Image 1

Mediaedge

The project consists of the strip out and re-fitting out of a building at 1-2 Paris Gardens, the project is 45,000 sq ft over Lower Ground, Ground, First, Second, Third and Fourth Floors.

The works were carried out in a fully occupied building over three phases as follows:

  • Phase One - Fourth, Second, Ground and Lower Ground
  • Phase Two - First and Third Floors
  • Phase Three - Lower Ground, Board Rooms, Training Room, Common parts and storage areas

The works consisted of new fresh air and part air conditioning, new lighting throughout, refurbishment of twenty one WC's and four showers, new cellularisation, Reception area, kitchens café bar area, all common parts, redecoration throughout including blinds, carpets and feature artwork.

Special features include specialist joinery for tea points, copy parts, reception desk, bar, library areas, spray booths, banquette seating, credenzas, new bar and feature pin boards. The fit-out included new Cat 6 voice and data wiring and audio vishual installation.

The project was carried out over twenty a twenty week period; Phase One was twelve weeks, Phase Two was seven weeks and Phase Three one week.

Project Details
Client   Mediaedge
 Project Manager Bollingbrook 
 Architect BDG Workfutures 
 Form of Contract  
 Value £1.4M 
 Size 45,000 sq ft 
 Programme Period 20 weeks 